Project Duration
Stipulated Date of Commencement
June 09 2009
Stipulated Date of Completion /
Likely Date of Completion September 07 2009
Likely Date of Completion September 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,343,352.00
Awarded for
₹ 4,609,470.95
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Effective Architectural Services