Project Duration
Stipulated Date of Commencement
November 05 2018
Stipulated Date of Completion /
Likely Date of Completion February 04 2019
Likely Date of Completion February 04 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,280,454.50
Awarded for
₹ 2,238,626.00
Project highlights
Replacement of failed cables and supply, installation of new fixtures, spares for the streetlights
Contractors
M/s. James Electrical