Project Duration
Stipulated Date of Commencement
December 10 2018
Stipulated Date of Completion /
Likely Date of Completion August 24 2019
Likely Date of Completion August 24 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,535,793.84
Awarded for
₹ 8438797.59
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Supply & Installation of Desks & Chairs for Government Schools/Colleges in the state of Goa- Part-III
View Project
Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-D
View Project
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari taluka – Package P-Balance works.
View Project





