Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion November 15 2019
Likely Date of Completion November 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,482,356.00
Awarded for
₹ 18,417,000.00
Project highlights
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka
Contractors
M/s. Mahabaleshwar M. Naik & Co.
Consultants
M/s. Bhaskar Wagle & Associates
See Similar Projects
Construction of Hostel at Government College of Arts, Science & Commerce at Sanquelim, Goa – Balance work
View Project
Supply, Installation, Testing & Commissioning of CCTV & PA System
View Project
Repairs/ Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical – GHS Colomb
View Project





