Project Duration
Stipulated Date of Commencement
July 26 2019
Stipulated Date of Completion /
Likely Date of Completion August 04 2020
Likely Date of Completion August 04 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,666,709.00
Awarded for
₹ 14,181,390.28
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. UVR Developers
Consultants
M/s. Nitin Arolkar