Project Duration
Stipulated Date of Commencement
November 30 2019
Stipulated Date of Completion /
Likely Date of Completion November 08 2020
Likely Date of Completion November 08 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,768,360.00
Awarded for
₹ 11,437,653.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Neha Eleccon Services Pvt. Ltd
Consultants
M/s. Nitin Arolkar