Project Duration
Stipulated Date of Commencement
September 04 2019
Stipulated Date of Completion /
Likely Date of Completion March 13 2020
Likely Date of Completion March 13 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,228,121.00
Awarded for
₹ 6,461,335.69
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Prashant Rangrao Desai
Consultants
M/s. Nitin Arolkar
See Similar Projects
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Fire Fighting work
View Project
Construction of building for Boys’ hostel at Goa University Campus – Civil & Plumbing works
View Project
Repairs/Upgradation & Maintenance of Government schools in the State of Goa – Quepem Taluka – Package F.
View Project





