Project Duration
Stipulated Date of Commencement
June 28 2018
Stipulated Date of Completion /
Likely Date of Completion March 11 2019
Likely Date of Completion March 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,049,600.00
Awarded for
₹ 10,973,975.15
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode
See Similar Projects
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package IV (GPS Hauliwada, GPS Kalsai, GPS Camarconda, GPS Matoje, GPS Panaswada)
View Project
Repairs/Upgradation and maintenance of Govt. schools in the State of Goa-Civil, Plumbing and Electrical works -Salcete Taluka-Package B (GPS Baradi, GPS Chandor, GMS Sao Jose de Areal, GPS Gudi Paroda)-4th CALL.
View Project
Repairs/Upgradation & maintenance of Government schools in the state of Goa – Tiswadi taluka – Package-I (GPS Dhulapi, GPS Mangoda, GPS Gawant, GPS Akhada)
View Project