Project Duration
Stipulated Date of Commencement
August 04 2019
Stipulated Date of Completion /
Likely Date of Completion June 03 2020
Likely Date of Completion June 03 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,949,215.00
Awarded for
₹ 6,649,731.26
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Sharanya Infra Pvt. Ltd.
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Repairs/ Upgradation & Maintenance of Government schools in the State of Goa –Civil, Plumbing & Electrical works in Bardez Taluka :- GPS Betim, GPS Salvaor do Mund, GPS Paithona