Project Duration
Stipulated Date of Commencement
May 03 2018
Stipulated Date of Completion /
Likely Date of Completion March 16 2019
Likely Date of Completion March 16 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,154,203.78
Awarded for
₹ 18,722,224.15
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode