Project Duration
Stipulated Date of Commencement
September 11 2018
Stipulated Date of Completion /
Likely Date of Completion July 25 2019
Likely Date of Completion July 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,554,175.00
Awarded for
₹ 8,534,225.25
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-
Contractors
M/s.Shrusti Construction
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
External Development works
View Project
Extension to middle school at Shristhal Canacona.
View Project
Construction of Anganwadi Centres from NABARD Assistance – Package VI (GPS Betmoddi Kakoda, GPS Bendurdem, GPS Cumbeabhat Velim).
View Project





