Project Duration
Stipulated Date of Commencement
September 27 2018
Stipulated Date of Completion /
Likely Date of Completion October 12 2019
Likely Date of Completion October 12 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,791,190.00
Awarded for
₹ 22,795,741.42
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s.Guru Constructions
Consultants
M/s. Bhaskar Wagle and Associates