Project Duration
Stipulated Date of Commencement
March 22 2019
Stipulated Date of Completion /
Likely Date of Completion November 21 2019
Likely Date of Completion November 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,631,932.00
Awarded for
₹ 13,137,753.68
Project highlights
Repairs/Upgradation & Maintenance of Government Schools
Contractors
M/s. Shri Hari Krishna Constructions
Consultants
M/s. Bhaskar Wagle & Associates