Project Duration
Stipulated Date of Commencement
August 19 2019
Stipulated Date of Completion /
Likely Date of Completion April 18 2020
Likely Date of Completion April 18 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,016,611.35
Awarded for
₹ 18,098,805.51
Project highlights
Repairs, Upgradation & Maintenance work, civil, plumbing, Electrical etc.
Contractors
M/s. Shri. Mukesh Mandana
Consultants
M/s. Creative Abode
See Similar Projects
Infrastructure Works for Sanjay Centre for Special Education at Porvorim – Supply, Installation, Testing and Commissioning of 11kV HT Sub Station
View Project
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system
View Project
Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project