Project Duration
Stipulated Date of Commencement
November 08 2019
Stipulated Date of Completion /
Likely Date of Completion July 07 2020
Likely Date of Completion July 07 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,361,545.00
Awarded for
₹ 12,280,299.49
Project highlights
Repairs/Upgradation of School
Contractors
M/s. Shri Hari Krishna Constructions
Consultants
M/s Anil Chavda and Associates