Project Duration
Stipulated Date of Commencement
September 26 2018
Stipulated Date of Completion /
Likely Date of Completion June 05 2019
Likely Date of Completion June 05 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,008,643.34
Awarded for
₹ 9,974,507.49
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Anish Associates
Consultants
M/s. Nitin Arolkar