Project Duration
Stipulated Date of Commencement September 29 2018
Stipulated Date of Completion /
Likely Date of Completion
July 14 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,039,750.00
Awarded for ₹ 9,234,882.08

Project highlights

Repairs/ Upgradation & Maintenance of schools

 
Gallery Image
Contractors
M/s. Nilambari Construction
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and maintenance of Government schools in the state of Goa -Package F (GPS Rive, GPS Thane, GPS Shir)

View Project
Similar Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka : Package-K (GHS Sawardem, GPS Tem Uste, GPS Massordem, GPS Velus, GPS Sawantwada Pal, GPS Sawardem)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.