Project Duration
Stipulated Date of Commencement
March 07 2019
Stipulated Date of Completion /
Likely Date of Completion November 20 2019
Likely Date of Completion November 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,795,370.00
Awarded for
₹ 13,724,359.85
Project highlights
Repairs/Upgradation of School
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode.
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka: Package-E (GPS Mhalshekarwada Parye, GPS Dhatwada Padoshe, GPS Rawan, GPS Gaonkarwada Honda, GHS Bhuipal)
View Project
Repairs/ Upgradation & Mainrenance ofGovemment Schools in the State ofGoa – Civil, Plumbing & Electrical works – Package – III (Tiswadi & Ponda Taluka) [Also falls in Ponda, St. Andre, Panaji and Cumbarjua]
View Project
Re-civil, plumbing and electical works- Salcete Taluka-Package A (GPS Ghantomorad, GPS Davorlim Maruti Mandir, GPS Seraulim, GPS Telaulim).
View Project





