Project Duration
Stipulated Date of Commencement June 22 2015
Stipulated Date of Completion /
Likely Date of Completion
October 21 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,976,710.00
Awarded for ₹ 3,976,710.00

Project highlights

Repair/Upgrdation works of schools which includes roofing , tiling,dadoes,painting etc.

 
Gallery Image
Contractors
M/s.Duracore Constructions
Gallery Image
Consultants
M/s.Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & maintenance of Government SchoolS in State of Goa – Civil, Plumbing & Electrical works – Package B (Quepem Taluka) – GPS Borimal, GPS Gajanan, GPS Chinchnagar, GPS Kamral, GPS Kumbharwada Sirvoi

View Project
Similar Project

Repairs/Upgradation and maintenance of Government High School at Headland Sada, Vasco, Goa.

View Project
Similar Project

Repairs/ Upgradation & Maintaince of Government schools in the State of Goa – Bardez Taluka-Package I – B

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.