Project Duration
Stipulated Date of Commencement
December 13 2018
Stipulated Date of Completion /
Likely Date of Completion August 28 2019
Likely Date of Completion August 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,991,491.00
Awarded for
₹ 11,799,520.48
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works
Contractors
M/s.Guru Constructions
Consultants
M/s. Vaishali Pednekar Associates