Project Duration
Stipulated Date of Commencement
August 03 2018
Stipulated Date of Completion /
Likely Date of Completion July 03 2019
Likely Date of Completion July 03 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,726,550.06
Awarded for
₹ 16,166,241.78
Project highlights
Repairs/ upgradation of schools which include proviison of new double skin galvalum sheet roofing, tiling, painting etc.
Contractors
M/s.A.Y Gulumkar
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Upgradation Of Government College of Pernem, Goa – Multipurpose Hall – Additional works
View Project
Repairs/ upgradation of GPS at Sanvordem
View Project
Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )
View Project