Project Duration
Stipulated Date of Commencement
August 03 2018
Stipulated Date of Completion /
Likely Date of Completion July 03 2019
Likely Date of Completion July 03 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,726,550.06
Awarded for
₹ 16,166,241.78
Project highlights
Repairs/ upgradation of schools which include proviison of new double skin galvalum sheet roofing, tiling, painting etc.
Contractors
M/s.A.Y Gulumkar
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Ponda Taluka: Package-C (GPS Kaungal Savai Verem, GPS Pali Savai Verem, GPS Savai Verem & GPS Vagurme Savai Verem)
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa -Civil, Plumbing and Electrical works- Salcete Taluka- Package E (GPS Assolna, GPS Maina Curtorim, GPMS Bhati Curtorim, GPS Telaulim) (2nd call)
View Project
Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco – Electrical, Lift and Fire Fighting Works
View Project