Project Duration
Stipulated Date of Commencement
June 20 2021
Stipulated Date of Completion /
Likely Date of Completion October 17 2021
Likely Date of Completion October 17 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,658,751.00
Awarded for
₹ 11,264,964.00
Project highlights
Electrical wiring, SITC of electrical substation at three existing sheds
1) Organic waste management facility behind Heera petrol pump patto.
2) Waste Management facility opposite LIC building at Patto.
3) Material recovery facility at St. Inez in panaji.
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates