Project Duration
Stipulated Date of Commencement September 08 2004
Stipulated Date of Completion /
Likely Date of Completion
October 07 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 350,184.40
Awarded for ₹ 366,922.00
 
Gallery Image
Contractors
M/s. Sandesh C. Naik
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Sewage Treatment Plant including sewage network at Institute of Psychiatry & Human Behaviour complex at Bambolim, Goa -Construction of building and sewage pipeline work

View Project
Similar Project

Fire fighting, fire alarm and PA System works

View Project
Similar Project

Construction of Primary Health Centre at Navelim, Margao, Goa. – Supply, Installation, Testing & Commissioning of 200 A Distribution BOX.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.