Project Duration
Stipulated Date of Commencement
October 21 2021
Stipulated Date of Completion /
Likely Date of Completion August 30 2024
Likely Date of Completion August 30 2024
Status
35%
Completed
Cost (₹)
Estimated at
₹ 4,451,677.00
Awarded for
₹ 3,499,308.00
Project highlights
The scope of work includes stagelighting and drapery system for Auditorium.
Contractors
M/s. Canara Lighting Industries Pvt. Ltd
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd