Project Duration
Stipulated Date of Commencement
May 22 2018
Stipulated Date of Completion /
Likely Date of Completion May 21 2020
Likely Date of Completion May 21 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,650,299.00
Awarded for
₹ 3,650,299.00
Contractors
M/s.ThyssenKrupp Elevator (India) Pvt
Consultants
In-house (GSIDC)