Project Duration
Stipulated Date of Commencement February 12 2015
Stipulated Date of Completion /
Likely Date of Completion
May 11 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,524,278.45
Awarded for ₹ 32,955,460.00

Project highlights

Upgraded premises for the Goa Human Resource Development Corporation at Porvorim, Goa

 
Gallery Image
Contractors
M/s. Concept Creators
Gallery Image
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators for various projects in Goa.

View Project
Similar Project

Fabrication of Sloping roof on terrace of Block A building of EDC House, Panaji

View Project
Similar Project

Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim- Goa. Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.