Project Duration
Stipulated Date of Commencement February 12 2015
Stipulated Date of Completion /
Likely Date of Completion
May 11 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,524,278.45
Awarded for ₹ 32,955,460.00

Project highlights

Upgraded premises for the Goa Human Resource Development Corporation at Porvorim, Goa

 
Gallery Image
Contractors
M/s. Concept Creators
Gallery Image
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Fumehood, Blowers and Ducting work

View Project
Similar Project

Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.

View Project
Similar Project

Solid Waste Management during St. Francis Xavier Exposition 2014 – 2015 at Old Goa including sweeping, door to door colleciton, soiling and segregation, transportation and bailing of Municipal waste.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.