Project Duration
Stipulated Date of Commencement
June 21 2017
Stipulated Date of Completion /
Likely Date of Completion July 05 2017
Likely Date of Completion July 05 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 653,125.00
Awarded for
₹ 863,265.00
Contractors
M/s. A.G. Pushpakaran
Consultants
M/s. Effective Architectural Services