Project Duration
Stipulated Date of Commencement January 25 2007
Stipulated Date of Completion /
Likely Date of Completion
November 24 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 39,118,679.00
Awarded for ₹ 42,524,358.16

Project highlights

Demolition of old structures and construction of new RCC structure, supply & installation of c-tech machinery and upgradation of existing units.

 
Gallery Image
Contractors
M/s. Gharpure Engineering and Constructions Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation and Testing and Commissioning of Xenon Headlight System

View Project
Similar Project

Rear Side parking and Biomedical Waste Building

View Project
Similar Project

Maintenance/Renovation works of Community Health Centre at Valpoi S.H.- Maintenance of Air Conditioners

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.