Project Duration
Stipulated Date of Commencement
January 25 2007
Stipulated Date of Completion /
Likely Date of Completion November 24 2007
Likely Date of Completion November 24 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39,118,679.00
Awarded for
₹ 42,524,358.16
Project highlights
Demolition of old structures and construction of new RCC structure, supply & installation of c-tech machinery and upgradation of existing units.
Contractors
M/s. Gharpure Engineering and Constructions Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd