Project Duration
Stipulated Date of Commencement August 19 2014
Stipulated Date of Completion /
Likely Date of Completion
August 18 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rate contract Rs. 3,00,00,000.00
Awarded for ₹ Rate contract Rs. 3,00,00,000.00

Project highlights

Refurbishment of ornamental poles

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Setting up of software technology park at Udyog Bhavan, Panaji, Goa- Dismantling civil and plumbing works

View Project
Similar Project

Dehumidification System.

View Project
Similar Project

Civil and Plumbing works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.