Project Duration
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Awarded for
₹ 39,436,314.45
Project highlights
The old Panchayat ghar was in dilapidated condition and hence the new building was constructed
Contractors
Consultants