Project Duration
Stipulated Date of Commencement June 22 2015
Stipulated Date of Completion /
Likely Date of Completion
July 21 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 571,816.35
Awarded for ₹ 654,957.00

Project highlights

Providing 11 KV transformer substation for releasing of electrical power supply to Commercial Tax Office, Ponda .

 
Gallery Image
Contractors
M/s. S. Electricals
Gallery Image
Consultants
M/s Saolapurkar & Associates
 
Similar Projects

See Similar Projects

Similar Project

Internal, external and special lighting fixtures (Part B : External lights and façade lighting)

View Project
Similar Project

Additional electrical and networking work.

View Project
Similar Project

Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.