Project Duration
Stipulated Date of Commencement September 01 2015
Stipulated Date of Completion /
Likely Date of Completion
September 30 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 482,628.00
Awarded for ₹ 446,140.00

Project highlights

Providing 11 KV transformer substation for releasing of electrical power supply to Commercial Tax Office,Vasco.

 
Gallery Image
Contractors
M/s. Karant Electricals
Gallery Image
Consultants
M/s. Saolapurkar and Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of compound wall at Calangute / Saligao in North Goa.

View Project
Similar Project

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

View Project
Similar Project

CPOE switches

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.