Project Duration
Stipulated Date of Commencement
November 18 2016
Stipulated Date of Completion /
Likely Date of Completion January 17 2017
Likely Date of Completion January 17 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,706,391.69
Awarded for
₹ 3,748,767.75
Project highlights
The Operation Tables supplied at new burns ward at GMC will help in perform surgical procedures.
Contractors
M/s. Medex India Pvt. Ltd.
Consultants
In-house (GSIDC)