Project Duration
Stipulated Date of Commencement
November 18 2016
Stipulated Date of Completion /
Likely Date of Completion January 17 2017
Likely Date of Completion January 17 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,706,391.69
Awarded for
₹ 3,748,767.75
Project highlights
The Operation Tables supplied at new burns ward at GMC will help in perform surgical procedures.
Contractors
M/s. Medex India Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance /Renovation Work of Sub District Hospital at Ponda, Goa – Supply, Installation, Testing and Commissioning of SMF batteries including buyback of old SMF batteries
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Emerson make 40 KVA UPS system installed at Goa Medical College for three years
View Project
Steel Operation Theatre work.
View Project