Project Duration
Stipulated Date of Commencement
October 25 2021
Stipulated Date of Completion /
Likely Date of Completion July 03 2022
Likely Date of Completion July 03 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 67,034,857.00
Awarded for
₹ 76,417,279.80
Project highlights
Bridge work
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Architecture Autonomous