Project Duration
Stipulated Date of Commencement
November 14 2017
Stipulated Date of Completion /
Likely Date of Completion December 14 2017
Likely Date of Completion December 14 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,019,832.00
Awarded for
₹ 8,371,107.76
Project highlights
Painting of buildings for IFFI 2017
Contractors
M/s.Rakesh Kambli
Consultants
M/s.Vaishali Pednekar & Associates
See Similar Projects
Replacement of failed cables and supply, installation of new fixtures, spares for the streetlights along D.B. Marg from Kadamba Bus stand to Miramar Circle (IFFI 2018)
View Project
Interiors and Furniture work.
View Project
Construction of Laboratories for Agricultural Department at Ella Old Goa and Margao.
View Project