Project Duration
Stipulated Date of Commencement
November 06 2017
Stipulated Date of Completion /
Likely Date of Completion February 05 2018
Likely Date of Completion February 05 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,152,058.00
Awarded for
₹ 17,938,403.00
Project highlights
Construction of fencing/ railing along DB Road and other civil repair works
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Vaishali Pednekar Associates