Project Duration
Stipulated Date of Commencement November 30 2020
Stipulated Date of Completion /
Likely Date of Completion
March 10 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,678,633.00
Awarded for ₹ 36,51,527.60 part amount of 83,24,187.60

Project highlights

Exterior and Interior painting works at Community Health Centre, Bicholim, Community Health Centre, Tuem

 
Gallery Image
Contractors
M/s.H. Candolcar & Sons
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Supply & Installation of Lead Doors & Lead Glass

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – SH: Dismantling and buy back of existing Sewage Treatment Plant (STP) and Design, Supply, Installation, Testing and Commissioning of new 30 KLD STP at Community Health Centre, Canacona – Goa

View Project
Similar Project

Rear Side parking and Biomedical Waste Building

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.