Project Duration
Stipulated Date of Commencement
November 12 2013
Stipulated Date of Completion /
Likely Date of Completion November 11 2014
Likely Date of Completion November 11 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,025,750.00
Awarded for
₹ 2,044,000.00
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Deshpande Constructions
Consultants
In-house (GSIDC)