Project Duration
Stipulated Date of Commencement June 06 2020
Stipulated Date of Completion /
Likely Date of Completion
July 05 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 510,587.00
Awarded for ₹ 379,000.00

Project highlights

Supply and Installation of on-line UPS system of 10kVA capacity for Virology lab and batteries at Casualty, Ward 143, MS office, Lecture Hall and Examination Hall.

 
Gallery Image
Contractors
M/s. Solar Enterprise
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance /Renovation Work of Sub District Hospital at Ponda, Goa – Supply, Installation, Testing and Commissioning of SMF batteries including buyback of old SMF batteries

View Project
Similar Project

Renovation/ Maintenance of Hospitals, CHCs, PHC’S, RMD’s under Directorate of Health Services in South Goa – S.H- Renovation/ Maintenance work of Primary Health Centre at Shiroda:Maintenance Contract of the Otis Make Passenger Elevator installed at PHC, Shiroda for the period of three years

View Project
Similar Project

Mortuary Cabinet.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.