Project Duration
Stipulated Date of Commencement
September 27 2019
Stipulated Date of Completion /
Likely Date of Completion September 26 2021
Likely Date of Completion September 26 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,65,29,794.00
Awarded for
₹ 9,29,21,300.00
Project highlights
Painting of Hospital Buildings
Contractors
M/s. H. Candolkar & Sons
Consultants
In-house (GSIDC)