Project Duration
Stipulated Date of Commencement July 06 2018
Stipulated Date of Completion /
Likely Date of Completion
July 05 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 60,000.00
Awarded for ₹ 60,000.00

Project highlights

Maintenance contract of 180 KVA DG set for a period of three years

 
Gallery Image
Contractors
M/s. Trinity Mahalasa Durga Sales & Services
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Fabrication of Sloping roof on terrace of Block A building of EDC House, Panaji

View Project
Similar Project

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa

View Project
Similar Project

Supply, installation, testing & commissioning of Interactive LED Panels and Video Conferencing system at newly constructed Office Building for Department of Forest at Altinho Old IPHB Complex

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
    Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.