Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
June 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,960,000.00
Awarded for ₹ 20,00,000.00
 
Gallery Image
Contractors
M/s. Thyssenkrupp Elevators (P) Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 