Project Duration
Stipulated Date of Commencement
August 10 2010
Stipulated Date of Completion /
Likely Date of Completion July 10 2011
Likely Date of Completion July 10 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,852,975.00
Awarded for
₹ 4,026,350.00
Contractors
M/s.ThyssenKrupp (I) Pvt Ltd
Consultants
M/s. Effective Architectural Services