Project Duration
Stipulated Date of Commencement November 15 2005
Stipulated Date of Completion /
Likely Date of Completion
December 15 2005
Status
100%
Completed
Cost (₹)
Estimated at ₹ 611,117.00
Awarded for ₹ 641,000.00

Project highlights

The laying of paver blocks was taken up on the balance portion of the promenade on the riverside from Patto bridge to Miramar circle.

 
Gallery Image
Contractors
M/s. D. K. Bhomkar
Gallery Image
Consultants
M/s. Prabhugaonker & Associates
 
Similar Projects

See Similar Projects

Similar Project

Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Porvorim

View Project
Similar Project

Design and construction of bridge over river Satrem at Satrem, Sattari Taluka.

View Project
Similar Project

Development of infrastructure for Panaji Minor Port : Construction of Jetty at Brittona.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.