Project Duration
Stipulated Date of Commencement
October 09 2012
Stipulated Date of Completion /
Likely Date of Completion September 10 2012
Likely Date of Completion September 10 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,923,512.21
Awarded for
₹ 3,083,239.00
Contractors
M/s. Vrindanvan Agricultural Services
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.