Project Duration
Stipulated Date of Commencement
January 28 2019
Stipulated Date of Completion /
Likely Date of Completion January 27 2022
Likely Date of Completion January 27 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,999,585.90
Awarded for
₹ 5,571,750.00
Project highlights
Landscaping Work
Contractors
M/s. Limboo Softscape
Consultants
In-house (GSIDC)