Project Duration
Stipulated Date of Commencement August 30 2004
Stipulated Date of Completion /
Likely Date of Completion
December 26 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 19,938,000.00
Awarded for ₹ 20,933,000.00

Project highlights

1) Hard landscaping like compound wall, paved plazas, semi-paved decks, spaces, kerbs, parking areas, café sitouts, planter boxes, etc.
2) Soft landscaping like lawns, vases, trees, specimen plants, shrubs, rockery, pebbles and also includes services like stormwater drainage, external electrical works, landscape plumbing and street furniture.

 
Gallery Image
Contractors
M/s. R. B. S. Candiaparcar
Gallery Image
Consultants
M/s. Prabhugaonker & Associates
 
Similar Projects

See Similar Projects

Similar Project

Supply and erection of new 11KV line with AB conductor from 33/11KV colony substation to M/s.Rajiv Gandhi Kala Mandir

View Project
Similar Project

Construction of Washrooms at Old Goa for Exposition 2014 – Package II – Near Se Cathedral Church and St. Cajetan Church.

View Project
Similar Project

RFID System.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.