Project Duration
Stipulated Date of Commencement
December 25 2010
Stipulated Date of Completion /
Likely Date of Completion May 24 2011
Likely Date of Completion May 24 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,61,21,471.00
Awarded for
₹ 13,418,362.92
Project highlights
Internal & External works for Ravindra Bhavan
Contractors
M/s. Power & Instrumentation (Guj) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.