Project Duration
Stipulated Date of Commencement July 11 2014
Stipulated Date of Completion /
Likely Date of Completion
August 10 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,76,42,076.00
Awarded for ₹ 19,688,390.00
 
Gallery Image
Contractors
M/s. Floor-Space
Gallery Image
Consultants
M/s. Effective Architectural Services
 